Bridge Construction Plant and Equipment

Bridge Construction Plant and Equipment: 50 Example Fleets by Work Type

This page provides over 50 example plant and equipment mixes for different types of
bridge construction and rehabilitationroad and rail bridges, overpasses, underpasses,
culverts, urban viaducts, segmental, launched, temporary works and maintenance.

Each card represents a practical plant + equipment fleet that works together as a system.
Use these as starting points when developing methodology‑led estimates, programmes and
Efficient Construction Cost (ECC) models. Always adjust for your specific
geometry, access, headroom, traffic/rail constraints, geology and safety rules.

Foundations & Substructure

1. Bored Piles for Highway Bridge

Use case: Deep drilled shafts for piers and abutments.

Plant & Equipment Mix

  • 1–2 × Large bored piling rigs (Kelly bar/CFA as specified)
  • 1 × Casing oscillator / rotary head (if required)
  • 1 × Concrete pump and multiple agitator trucks
  • 1–2 × 80–150 t cranes for cages and casings
  • 1–2 × 20–30 t excavators for spoil and platform management

2. Driven Steel H‑Piles for Rail Bridge

Use case: High‑capacity piles in rail corridor with limited windows.

Plant & Equipment Mix

  • Crawler crane (100–150 t) with leaders
  • Diesel or hydraulic impact hammer
  • Excavator for pre‑auger or pre‑drilling (if needed)
  • Hi‑rail or rubber‑tyred crane (if working from rail level)

3. CFA Piles for Urban Overbridge

Use case: Low‑noise foundations near sensitive receivers.

Plant & Equipment Mix

  • CFA piling rig with spoil handling system
  • Concrete pump line and agitators
  • Small crane/telehandler for reinforcement cages
  • Excavator for trimming and spoil management

4. Piled Bridge Abutment on Soft Ground

Use case: Bridge abutments over compressible soils.

Plant & Equipment Mix

  • Piling rig (CFA or bored as per design)
  • Excavator for abutment excavation and backfill
  • Compaction plant (sheepsfoot/smooth drum)
  • Small crane for reo and formwork

5. Pile Cap & Pier Construction

Use case: RC pile caps and piers in road or rail environment.

Plant & Equipment Mix

  • Formwork/falsework systems
  • 80–150 t crane for reo and shutters
  • Concrete boom/line pump and agitators
  • Excavator for local trimming and backfill

6. Pier Construction in Water (River Bridge)

Use case: Piers founded in a river or tidal channel.

Plant & Equipment Mix

  • Barge with 150–250 t crawler crane
  • Temporary cofferdam or caisson system
  • Pump sets and dewatering system
  • Workboat/tug for barge positioning

Short to Medium Span Bridges – Precast Beams

7. Highway Overpass – Precast I‑Beams

Use case: Multi‑span overpass over busy road or rail.

Plant & Equipment Mix

  • 2 × 250–400 t mobile cranes (dual beam lifts)
  • 1 × 80–120 t assist crane
  • Telehandler for diaphragms and deck components
  • MEWPs for bearing and diaphragm works

8. Rail Overbridge – Night Beam Install

Use case: Bridge beams installed in limited possessions.

Plant & Equipment Mix

  • 300–500 t mobile crane (truck or crawler, depending on site)
  • Rail protection plant (hi‑rail vehicles/barriers)
  • MEWPs for crosshead and shear key works
  • Lighting towers and temporary traffic/rail control equipment

9. Precast Slab Bridge Over Local Road

Use case: Simple single or 2‑span slab bridge.

Plant & Equipment Mix

  • 100–200 t mobile crane
  • Crane truck for precast slabs and barrier units
  • Concrete line pump for joints and toppings
  • Small MEWPs for edge works

10. Rural Bridge Replacement – Short Closure

Use case: Replace small timber/old bridge with precast deck unit.

Plant & Equipment Mix

  • 80–150 t mobile crane
  • 20–30 t excavator for old deck and abutment works
  • Small roller and compactor for approach embankments
  • Light trucks for guardrails and finishes

Long Span, Segmental & Launched Bridges

11. Incrementally Launched Concrete Bridge

Use case: Multi‑span viaduct launched from one abutment.

Plant & Equipment Mix

  • Launching bed with form travellers and jacks
  • Launching nose and sliding bearings
  • Tower crane(s) or mobile cranes for rebar and formwork
  • Concrete batching plant or reliable supply + pumps

12. Balanced Cantilever Segmental Bridge

Use case: Long spans over river, road or rail with limited falsework.

Plant & Equipment Mix

  • Form travellers (one or more pairs)
  • 150–300 t crawler cranes for segment material handling
  • Concrete pumps for in‑situ segments or match‑cast units
  • Pre‑stressing equipment and jacks

13. Precast Segmental Viaduct with Launching Girder

Use case: Urban or rail viaduct with precast segments erected by girder.

Plant & Equipment Mix

  • Launching gantry/girder
  • Segment delivery trucks or SPMTs
  • Strand jacks and lifting frames
  • Grout pumps and epoxy injection systems

14. Steel Box Girder Erection over River

Use case: Fixed/floating crane erection of steel girders.

Plant & Equipment Mix

  • Heavy lift barges with large crawler cranes
  • Support tugs and barges
  • Temporary towers and strand jacks (if incremental)
  • MEWPs for bolting and welding

15. Cable‑Stayed Bridge Pylon & Deck

Use case: Iconic cable‑stayed bridge in highway or rail application.

Plant & Equipment Mix

  • Tower cranes on pylons
  • Self‑climbing formwork for pylons
  • Strand jacks for cable stressing
  • Deck launching or segmental erection gear

Bridges Over Roads & Rail – Urban / Brownfield

16. Rail Overbridge in CBD – Tight Site

Use case: New bridge over rail corridor with limited crane pads.

Plant & Equipment Mix

  • Luffing jib tower crane (if permissible)
  • 350–500 t mobile crane for beam lifts in possessions
  • Mini excavators for abutments and services
  • MEWPs with restricted envelopes near OHW

17. Freeway Overpass over Live Traffic

Use case: Install beams with staged traffic diversions.

Plant & Equipment Mix

  • 300–600 t mobile crane (night/weekend lifts)
  • TMA trucks and traffic control plant
  • MEWPs for diaphragms and crossheads
  • Skid steers/mini excavators for abutment front works

18. Bridge Slide over Rail (Lateral Slide Method)

Use case: Build offline, slide into place in rail shutdown.

Plant & Equipment Mix

  • Temporary slide track and jacking system
  • Hydraulic jacks and control system
  • Crane(s) for temporary works assembly
  • Tamping machine/Hi‑rail excavator for track reinstatement

19. Incremental Jack‑Up of Existing Bridge for Bearing Replacement

Use case: Jack and support bridge for new bearings.

Plant & Equipment Mix

  • Hydraulic jacking system and temporary trestles
  • Small cranes/MEWPs for bearing removal/installation
  • Survey and monitoring instrumentation

Underpasses, Box Jacking & Culverts

20. Box Jacked Underpass Beneath Rail

Use case: Road underpass installed under rail formation.

Plant & Equipment Mix

  • Jacking frame and hydraulic jacks
  • 20–30 t excavator inside/leading box
  • 100–200 t crane to place pre‑cast box segments
  • Dozer/loader for spoil stockpiles
  • Pump sets for dewatering and settlement monitoring

21. Twin Box Culvert Under Road Embankment

Use case: Drainage/underpass culverts under existing highway.

Plant & Equipment Mix

  • 20–30 t excavator
  • 80–120 t crane for culvert units
  • Compactors for bedding and backfill
  • Watercart

22. Cut‑and‑Cover Underpass

Use case: Trench, build box, backfill and reinstate road/rail.

Plant & Equipment Mix

  • Excavators 30–40 t with breakers
  • Trench support/shoring system
  • Concrete pumps and cranes for reinforcement
  • Graders and rollers for approach reinstatement

Temporary Works, Falsework & Access

23. Full Falsework for In‑Situ Bridge Deck

Use case: Multiple spans on full falsework over dry ground.

Plant & Equipment Mix

  • Tower crane or 80–150 t mobile crane
  • Falsework/shoring towers and deck systems
  • Concrete boom pump
  • Scissor lifts for soffit access

24. Temporary Support Towers in Rail Corridor

Use case: Support girders over rail during construction.

Plant & Equipment Mix

  • Hi‑rail crane or mobile crane from side
  • Modular shoring towers
  • MEWPs for locking and bracing

25. Suspended Access Platforms Under Bridge

Use case: Maintenance works on soffit and girders.

Plant & Equipment Mix

  • Suspended platforms or under‑bridge units
  • MEWPs (truck‑mounted) where height/access permits
  • Rope access gear for difficult locations

26. Temporary Bailey/Modular Bridge

Use case: Temporary diversion bridge during replacement.

Plant & Equipment Mix

  • Crane (80–150 t) or telehandler for panel assembly
  • Rollers and jacks for launch
  • Excavators and compactors for approaches

Bridge Rehabilitation & Strengthening

27. Deck Replacement on Existing Bridge

Use case: Remove existing deck, install new precast/in‑situ deck.

Plant & Equipment Mix

  • 250–400 t mobile cranes for deck segments
  • Hydro‑demolition or saw‑cutting units
  • MEWPs and scaffolds for edge works

28. Bearing Replacement Programme

Use case: Replace bearings on multi‑span bridge.

Plant & Equipment Mix

  • Hydraulic jacks and temporary supports
  • MEWPs or under‑bridge units for access
  • Small crane truck for new bearings

29. Concrete Repair & Cathodic Protection

Use case: Patch repairs and CP on beams, piers and soffits.

Plant & Equipment Mix

  • Under‑bridge platform or scaffolding
  • Hydro‑demolition / chipping tools
  • Grout and shotcrete pumps
  • CP rectifiers and installation gear

30. FRP Strengthening of Girders and Slabs

Use case: Carbon fibre wrapping or laminates for capacity upgrade.

Plant & Equipment Mix

  • Access platforms (scaffold/under‑bridge)
  • Surface prep tools (grinders, shot blasters)
  • Mixers and application tools for resins

Small Bridges, Culverts & Rural Structures

31. Small Rural Road Bridge Replacement

Use case: Remove old timber, install precast deck or culvert.

Plant & Equipment Mix

  • 20–30 t excavator
  • 80–120 t mobile crane
  • Roller and grader for approaches
  • Concrete line pump (if required)

32. Rail Culvert Replacement in Possession

Use case: Replace culvert under track during shutdown.

Plant & Equipment Mix

  • Hi‑rail excavator or 20–30 t excavator beside track
  • 80–120 t mobile crane for culvert units
  • Tamper and regulator for ballast/tamping

33. Footbridge over Local Road or Rail

Use case: Lightweight steel or truss footbridge.

Plant & Equipment Mix

  • 200–300 t mobile crane
  • 50–80 t assist crane
  • MEWPs for finishing and connection works
  • Mini excavator for abutment and ramps

34. Pedestrian Boardwalk & Small Creek Crossings

Use case: Timber/steel walkway structures.

Plant & Equipment Mix

  • Mini excavator or tracked loader
  • Light crane truck
  • Hand tools and small plant

Bridge Maintenance & Inspection

35. Routine Visual Inspection of Highway Bridges

Use case: Network‑wide bridge inspection.

Plant & Equipment Mix

  • Under‑bridge inspection units (truck‑mounted)
  • MEWPs for abutment and pier access
  • Survey and NDT tools

36. Rail Bridge Inspection in Possessions

Use case: Detailed inspection of rail structures.

Plant & Equipment Mix

  • Hi‑rail inspection vehicle
  • Under‑bridge units or scaffolding
  • Portable NDT and crack detection kits

37. Joint Replacement & Waterproofing

Use case: Replace expansion joints and redo waterproofing.

Plant & Equipment Mix

  • Milling machine for asphalt around joints
  • Hydro‑demolition or saw‑cutting tools
  • Hot melt or strip seal installation equipment

38. Bridge Repainting / Steel Coating

Use case: Corrosion protection of steel girders and trusses.

Plant & Equipment Mix

  • Scaffolding or containment systems
  • MEWPs and/or rope access
  • Abrasive blasting or UHP water jetting equipment
  • Paint spray pumps and ventilation gear

Special Bridge Types – Arch, Movable & Timber

39. Steel Arch Bridge Erection

Use case: Tied arch or through arch bridge over river/valley.

Plant & Equipment Mix

  • Heavy lift cranes (land‑based or barge)
  • Temporary arch supports and guy systems
  • MEWPs and rope access for bolting/welding

40. Movable Bridge (Bascule/Lift) Machinery Installation

Use case: Mechanical and electrical systems for movable spans.

Plant & Equipment Mix

  • Mobile cranes / small gantries for machinery
  • MEWPs for machinery rooms
  • Alignment and commissioning equipment

41. Timber Bridge Replacement/Refurbishment

Use case: Rural or heritage timber bridges.

Plant & Equipment Mix

  • 20–30 t excavator and loader
  • Crane truck for timber girders and deck
  • Small rollers for approaches

Bridge Works with Rail & Road Interfaces

42. Rail Bridge Deck Replacement in Possession

Use case: Replace track‑carrying deck over road/water.

Plant & Equipment Mix

  • 300–500 t crane (from rail or road side)
  • Hi‑rail excavator for ballast and track
  • Tamper/regulator for track reinstatement
  • MEWPs for bearing and connection works

43. Road Over Rail Bridge with Traffic Switches

Use case: Build in halves with staged traffic diversions.

Plant & Equipment Mix

  • Excavators and dozers for embankments
  • Mobile cranes for beams
  • Graders and rollers for traffic switches
  • Traffic management plant (TMAs, VMS boards)

44. Integrated Bridge/Station Structure

Use case: Bridge forming part of station concourse or platform deck.

Plant & Equipment Mix

  • Tower crane or luffing crane (urban)
  • Mobile cranes for beams and precast elements
  • MEWPs and scaffolds for complex connections

Bridge Demolition & Full Replacement

45. Complete Demolition of Road Bridge

Use case: Demolish overpass during weekend shutdown.

Plant & Equipment Mix

  • 2–3 × 30–50 t excavators with shears and breakers
  • Skid steers and loaders for debris
  • Trucks for rubble removal
  • TMA vehicles and traffic management equipment

46. Controlled Demolition over Rail

Use case: Remove old bridge over rail with strict protection.

Plant & Equipment Mix

  • Mobile crane(s) to lift segments to safe area
  • Excavators with breakers away from rail
  • Protection screens and crash decks
  • Hi‑rail protection vehicles

47. Partial Demolition and Widening

Use case: Widen existing bridge with partial removal.

Plant & Equipment Mix

  • Hydro‑demolition / saw‑cutting units
  • Crane for removal of cut sections
  • Excavators for backfill and new works

48. Replacement of Old Timber Rail Bridge with Precast

Use case: Timber replacement in limited possessions.

Plant & Equipment Mix

  • Hi‑rail crane or 80–150 t mobile crane
  • Hi‑rail excavator for ballast and track work
  • Small tamper

49. Emergency Bridge Replacement (Flood/Damage)

Use case: Rapid deployment solution after failure.

Plant & Equipment Mix

  • Modular/temporary bridge system (Bailey or similar)
  • Mobile crane(s) and telehandlers
  • Excavators and compactors for quick approaches

50. Bridge Removal by SPMT & Ground‑Level Demolition

Use case: Move complete span onto demolition area.

Plant & Equipment Mix

  • Self‑Propelled Modular Transporters (SPMTs)
  • Jacking systems and temporary supports
  • Demolition excavators with shears/pulverisers

Need Help Selecting or Optimising Bridge Plant and Equipment Mixes?

These example fleets are starting points only. On a live bridge project, the optimal plant
and equipment mix depends on:

  • Span arrangement, structural form and geometry
  • Access (over water, over rail, over major roads) and headroom
  • Staging, possessions/closures and temporary works strategy
  • Required production, safety constraints and ECC/TOC objectives

We can help you:

  • Develop methodology‑led plant and equipment mixes for each bridge package
  • Align staging and access with realistic productivity and Efficient Construction Cost (ECC)
  • Compare lifting, launching and jacking options on a time–cost–risk basis
  • Feed real project learning back into future bridge bids and planning

Use the form below to discuss your project.

Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected!!!

We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.

Powered By
Best Wordpress Adblock Detecting Plugin | CHP Adblock