t-hr-el-10006-st HV Aerial Line Maintenance
t-hr-ci-12090-st Airspace and External Developments
SMS-06-GD-0268-working-around-electrical-equipment
HV Earthing for Substations and Distributions Systems TS 037261.0, EP 12 10 00 10 SP
NS130 Laying Underground cables up to and including 11kV
BCA-Report-Rev-2-95-Cudgegong-Road-Rouse-Hill
Transgrid_environment-handbook
NS174C Environmental Handbook Update (14th August 2017)
NS174C Environmental Handbook for Construction and Maintenance
NS174B Environmental Assessment Guidelines
NS174 Environmental Procedures 1.0 PURPOSE Network Standard NS174 outlines the environmental procedures to be adopted by all people involved in the planning, construction, maintenance...
NS190 Oil Containment Operational Requirements for Major Substations 1.0 PURPOSE This Network Standard details the general requirements for the operation of oil containment systems at major...
Ausgrid - Decommissioning and returning assets Authorised Accredited Service Providers may be required to decommission and return one or more Ausgrid assets as part of an approved network...
AUSGRID Decommissioning and returning assets (PDF - LINK) NS190 Oil Containment Operational Requirements for Major Substations (Construction Methodology - LINK) NS130 Laying Underground cables up to...