The Rix Group has successfully completed a complex intersection upgrade at Camp Mountain Road and Samford Road in Ferny Hills, demonstrating efficient project delivery under challenging time constraints while preserving adjacent conservation areas.

Technical Specifications

Component Quantity Implementation
Steel Mesh 1,031m² Surface stabilization
Shotcrete 213m³ Four-day application
Strip Drains Full coverage Drainage solution
Work Window 4 hours daily 9:00 AM – 1:00 PM
Conservation Area Minimal impact Environmental protection